Detailed design “Reconstruction of the existing tailings storage facility No. 2 of the Chadak Gold Recovery plant of the Almalyksky MMC JSC

Detailed design “Reconstruction of the existing tailings storage facility No. 2 of the Chadak Gold Recovery plant of the Almalyksky MMC JSC

This project is aimed at the reconstruction of the existing tailings storage facility No. 2 of the Chadak gold recovery plant of the Almalyksky MMC JSC, which is intended for the storage of tailings deposits

Our team provided the following types of services:

  • The stability of the projected dam and the possibility of increasing the volume of the tailings dam were calculated;
  • The calculation of the potential capacity of the tailing dump has been carried out;
  • An operation project has been developed and a technological map and regulations for filling the tailings storage have been developed.