The project is aimed at the reconstruction and modernization of the “Central” Boiler House in Shakhrisabz to improve the reliability, energy efficiency, and climate resilience of the central heating system (CHS).
Project Objective
The main objective of the project was to develop a concept and prepare a project assessment document for the reconstruction and modernization of the boiler house, focusing on improving efficiency, reliability, and climate adaptability.
Services Provided
Technical Component
-
Comprehensive diagnostics and infrastructure analysis
A detailed assessment of the existing CHS in Shakhrisabz was conducted, including the evaluation of equipment, pipelines, and auxiliary infrastructure. -
Conceptual equipment selection
Recommendations were developed for selecting and sizing the heat source (boiler house or individual heat station), heating devices, pumping equipment, and control and shut-off valves. -
Conceptual design of the CHS at the feasibility study stage
Pipeline layouts and the placement of all elements of the “Central” Boiler House were developed to ensure optimal system operation during reconstruction. -
Development of conceptual drawings
Preliminary drawings and diagrams were prepared for the project assessment stage, illustrating the main elements and functional connections of the system. -
Calculation of work volumes and comparison of equipment specifications
Work volumes were calculated, and technical characteristics of equipment were compared with project requirements. -
Preparation of cost estimates
Preliminary cost estimates were prepared to assess the expenses for the reconstruction and modernization of the boiler house.
Financial and Economic Component
-
Financial justification of the project
Investment calculations and financial flow analyses were developed to support project implementation. -
Economic feasibility analysis
An economic assessment was conducted, including evaluation of energy savings and efficiency improvements of the CHS.
Assessment of Technical Feasibility and Climate Resilience
The project included an evaluation of the technical feasibility of the boiler house reconstruction and an assessment of the CHS’s resilience to climate change and extreme conditions.
The results provide a foundation for reliable, energy-efficient, and climate-resilient operation of the “Central” Boiler House in Shakhrisabz